Friday, August 24, 2007

Flurry of activity



The bunker is complete inside and out. The final color coat on the stucco will be next week and the final paint as well. The electric run is dug and covered ready for Sierra to wire up.

Thursday, August 23, 2007

Peeling back the skin



All the form work has been removed, the site is being cleared and the work has started inside on the insulation.

Wednesday, August 22, 2007

All the concrete is finally poured





After a reluctant approval by the inspector who didn't like the way we do things in Florida, we were able to pour the last pad repair and complete the bunker. Also the tower pole went up and the backfill began.

Tuesday, August 21, 2007

Partial Pour



The inspector passed the satellite pads but failed the building with goofy comments. It is scheduled for inspection tomorrow and should be poured at noon.

The pad pour went fairly well but two of the forms moved and one will require repair and additional pour tomorrow.

Monday, August 20, 2007

Topping off the forms



The last of the forming work to pour the top deck is done and ready for inspection tomorrow. That is a lot of steel! The openings for the A/C units will be done tomorrow morning before the pour.

Saturday, August 18, 2007

Forming starts for the roof



Forming has started for the roof deck with the interior supports from scaffold. This should be done by Monday and Tuesday is the scheduled inspection/concrete pour.

Friday, August 17, 2007

Playing with blocks



After stripping the form, the blocks arrived. We set to work with a rented mixer building up our biceps throwing around the 40 pound blocks. The last of the 15 rows is up and we are ready to form the tie beam and roof deck.

Monday, August 13, 2007

Forming




Sheets of plywood and lengths of 2x4 are turned into forms for pouring the bunker slab and the satellite dish pads.After partially passing inspection we poured the first slab. The concrete was a little stiff but we managed the final finish.

Thursday, August 9, 2007

Hit the ground stumbling



When we arrived, we checked into a posh rental home then headed for work. The site had been excavated but unfortunately 5 feet off of the new site plan. This was discovered after two days of layout and forming work. All the holes were filled back in and re-excavated.